ARLC


Project Start Date: Mon 6/18/07
Project Finish Date: Wed 7/18/07

ARLC Tasks

Group Member NamesID
Name
DurationActual_DurationStart_DateFinish_DatePredecessorsPercent_Work_CompleteCost
Jon, William1
Proposal Approval
7 days7 daysFri 6/22/07Mon 7/2/07 100%$1,925.00
William2
Clean Up MDF - Purchase Equipment
1 day1 dayFri 6/22/07Mon 6/25/07 100%$75.00
Bryan, Jon, William3
Clean Up MDF - Planning
1 day1 dayThu 6/28/07Thu 6/28/072100%$625.00
Bryan, Jon, William4
Clean Up MDF - Installation of Patch Panel and Wall Mount
2 days2 daysFri 6/29/07Mon 7/2/073100%$1,225.00
Bryan, Jon5
Network Diagram and Documentation
3 days3 daysFri 6/29/07Tue 7/3/07 100%$625.00
Bryan6
Help Tutorials Build
3 days3 daysThu 7/5/07Mon 7/9/07 100%$975.00
Bryan, William7
Help Tutorial Testing
2 days2 daysThu 7/5/07Fri 7/6/07 100%$225.00
Bryan, William, Jon8
Help Tutorial Final Testing
1 day1 dayMon 7/9/07Mon 7/9/077100%$225.00
William9
Purchase of NAS
14 days2.33 daysFri 6/29/07Wed 7/18/07 6%$3,300.00
Bryan, Jon10
NAS Planning
1 day0 daysWed 7/11/07Wed 7/11/07 0%$625.00
Bryan, William Jon11
NAS Install
4 days0 daysFri 7/13/07Wed 7/18/07 0%$2,425.00
William12
Unforseen Help Desk
8 hrs8 hrsFri 6/29/07Fri 6/29/07 100%$200.00

ARLC Resources

NameScheduled_WorkCost
William85 hrs$2,125.00
Jon90 hrs$2,250.00
Bryan90 hrs$2,250.00