Project Start Date: Mon 6/18/07
Project Finish Date: Wed 7/18/07
Group Member Names | ID | Name | Duration | Actual_Duration | Start_Date | Finish_Date | Predecessors | Percent_Work_Complete | Cost |
---|---|---|---|---|---|---|---|---|---|
Jon, William | 1 | Proposal Approval | 7 days | 7 days | Fri 6/22/07 | Mon 7/2/07 | 100% | $1,925.00 | |
William | 2 | Clean Up MDF - Purchase Equipment | 1 day | 1 day | Fri 6/22/07 | Mon 6/25/07 | 100% | $75.00 | |
Bryan, Jon, William | 3 | Clean Up MDF - Planning | 1 day | 1 day | Thu 6/28/07 | Thu 6/28/07 | 2 | 100% | $625.00 |
Bryan, Jon, William | 4 | Clean Up MDF - Installation of Patch Panel and Wall Mount | 2 days | 2 days | Fri 6/29/07 | Mon 7/2/07 | 3 | 100% | $1,225.00 |
Bryan, Jon | 5 | Network Diagram and Documentation | 3 days | 3 days | Fri 6/29/07 | Tue 7/3/07 | 100% | $625.00 | |
Bryan | 6 | Help Tutorials Build | 3 days | 3 days | Thu 7/5/07 | Mon 7/9/07 | 100% | $975.00 | |
Bryan, William | 7 | Help Tutorial Testing | 2 days | 2 days | Thu 7/5/07 | Fri 7/6/07 | 100% | $225.00 | |
Bryan, William, Jon | 8 | Help Tutorial Final Testing | 1 day | 1 day | Mon 7/9/07 | Mon 7/9/07 | 7 | 100% | $225.00 |
William | 9 | Purchase of NAS | 14 days | 2.33 days | Fri 6/29/07 | Wed 7/18/07 | 6% | $3,300.00 | |
Bryan, Jon | 10 | NAS Planning | 1 day | 0 days | Wed 7/11/07 | Wed 7/11/07 | 0% | $625.00 | |
Bryan, William Jon | 11 | NAS Install | 4 days | 0 days | Fri 7/13/07 | Wed 7/18/07 | 0% | $2,425.00 | |
William | 12 | Unforseen Help Desk | 8 hrs | 8 hrs | Fri 6/29/07 | Fri 6/29/07 | 100% | $200.00 |
Name | Scheduled_Work | Cost |
---|---|---|
William | 85 hrs | $2,125.00 |
Jon | 90 hrs | $2,250.00 |
Bryan | 90 hrs | $2,250.00 |